GC buildout only / AV equipment excluded

Basement bids, simplified.

One job: compare GC/buildout cost. Theater AV gear, seats, projector, rack, speakers, screen, and controls are out. Theater construction items stay in.

Architectural sketch cover sheet for the renovation hub
Same field-set language as the hub, stripped down to the bid math.
Best baselineVictoryMost complete table shape today.
Robert adjusted$64K-$73KLow anchor after likely missing items.
Ben adjusted$124K-$130KPremium route after flooring/mirrors/mats.
PostureNo depositNormalize scope first.

Scorecard

Inclusion matrix first.

Grouped by Shell, Finishes, Theater Buildout, and Terms.

Green / included Red / missing Tan / partial or add-on Gray / unclear
Line Robert Victory Ben TVR FCI
Shell
Visible price Unclear Included Included Unclear Included
Room split Missing Included Partial Unclear Not applicable
Framing / drywall / paint Partial Included Included Unclear Not applicable
Outlets / lighting Unclear Included Included Unclear Not applicable
Finishes
Dance flooring Missing Included Missing Unclear Included
Gym rubber flooring Missing Included Missing Unclear Not applicable
Dance mirrors Missing Included Missing Unclear Not applicable
Theater Buildout
HVAC / noise handling Unclear Unclear Included Unclear Not applicable
Theater riser Unclear Unclear Included Unclear Not applicable
Fabric / acoustic wall system Missing Missing Included Unclear Not applicable
Decoupled soundproofing Missing Unclear Optional add-on Unclear Not applicable
Terms
Permits / design included Unclear Unclear Included Unclear Not applicable
Warranty / schedule / payment terms Unclear Unclear Unclear Unclear Not applicable
Sauna electrical Unclear Included Included Unclear Not applicable

Pick A GC

Tap one bid to see the practical read.

Same numbers, less scanning.

Victory

Base quote$78,836
Adjusted total$80K-$81K
Read

Best baseline because it is room-itemized and includes most finish items.

Missing / clarify

Permits, HVAC/noise treatment, riser, acoustic walls, specs, credits, warranty, schedule, payment terms.

Next ask

Ask for written permits/inspection owner, HVAC/noise scope, finish credits, warranty, schedule, and payment/change-order terms.

4-Column Compare

The smaller table.

GC, base quote, adjusted apples-to-apples, and what is missing.

GC / vendor Base quote Adjusted apples-to-apples What is missing
Robert & Son $33,500 $64K-$73K after allowances Flooring, mirrors, gym mats, sauna, theater specialty scope, permits/HVAC/warranty clarity.Negotiation anchor only.
Victory Remodeling $78,836 after discount $80K-$81K with FCI dance-floor swap Permits, HVAC/noise, riser, acoustic walls, warranty, specs, credits.Best comparison template.
Ben / Lifestyle Solutions $106,500-$111,000 $124K-$130K before discount Flooring, mirrors/glass, gym equipment, AV/furniture. Soundproofing/tray/star ceiling are add-ons.Premium theater-buildout path.
Trusted Veterans Pending TBD Actual prices and line items.Do not rank yet.
FCI $5,997-$7,309 Allowance only Not a GC: no walls, lighting, electrical, mirrors, mats, theater floor.Credit ruler only.

Apples To Apples

Add this to compare fairly.

Planning math only. Not a contractor commitment.

Vendor Quoted / base Add to normalize Comparable planning total Basis Caveat
Robert & Son $33.5K $30.6K-$39.0K $64.1K-$72.5K Add the visible finish package Robert does not itemize: LVP, gym mats, mirrors, lights, baseboards, sauna, and possibly outlets. Still below Ben's theater-construction scope.
Victory Remodeling $78.8K $0.9K-$2.2K if FCI replaces dance LVP $79.7K-$81.0K Only add the FCI delta over Victory's dance LVP line if you prefer the FCI floor. Theater riser/acoustic walls remain outside.
Ben / Lifestyle Solutions $106.5K-$111.0K $17.3K-$18.7K $123.8K-$129.7K Add flooring, gym mats, and mirrors/glass because Ben excludes them. Before any multi-room discount.
Trusted Veterans Pending TBD TBD No visible pricing yet. Needs the JobProgress detail.

Next Ask

Make every GC fill the same grid.

Room split, permits, HVAC/noise, flooring, mirrors, gym mats, sauna, riser, acoustic walls, warranty, schedule, payment terms, exclusions, and credits.